RWE and global investment firm KKR have reached financial close on two offshore wind projects in the UK, securing a financing package worth £12.8 billion and completing a 50:50 joint venture to develop the facilities.

The Vanguard West and Vanguard East projects, located in the North Sea off the Norfolk coast, will have a combined installed capacity of approximately 2.8 gigawatts (GW). Each development is expected to contribute 1.4GW of generation capacity, with both wind farms scheduled to be fully commissioned in 2030.

The projects represent a total investment of around £12 billion, including the wind farms and associated transmission infrastructure. Their financing combines equity commitments from RWE and KKR with non-recourse debt provided by a consortium of 35 international banks.

The companies described the financing as the largest non-recourse project financing secured for UK offshore wind to date. Financial close has now been reached for both developments, moving them into the next stage of delivery.

KKR completes 50% acquisition in each project

The financial close follows completion of the joint venture transaction announced by RWE and KKR in January 2026. KKR has acquired a 50% equity stake in both Vanguard West and Vanguard East, formally establishing equal ownership between the two partners.

The arrangement combines RWE’s experience in developing and operating offshore wind assets with KKR’s investment capital and infrastructure expertise. RWE will lead project delivery on behalf of the joint venture, while both companies will participate in the development, construction and operation of the wind farms.

KKR is funding its investment through capital accounts advised by the firm. The partnership gives the projects access to institutional investment alongside RWE’s offshore wind development capabilities.

For RWE, the transaction provides an investment partner for two capital-intensive developments while retaining an equal stake in both assets. For KKR, the agreement expands its exposure to large-scale energy infrastructure in the UK.

35 international banks support £12.8bn financing package

The project financing comprises £11.1 billion in cash facilities and a further £1.7 billion in ancillary facilities. A consortium of 35 international banks has provided the financing commitments.

The package also includes a £1 billion commitment from the UK’s National Wealth Fund, alongside credit cover from Germany’s Euler Hermes and Denmark’s Export and Investment Fund (EIFO).

RWE said the National Wealth Fund and Euler Hermes are participating in a UK offshore wind project financing for the first time. Their involvement, together with EIFO’s credit support, helped the joint venture meet its financing requirements.

RWE launched the financing process on behalf of the joint venture and worked with KKR’s Capital Markets team from the beginning of 2026 to execute the transaction.

The financing attracted demand from a broad group of lenders, with commitments covering the targeted amount. The debt package, combined with equity from RWE and KKR, provides the capital structure required to progress the two developments.

Non-recourse project financing is commonly structured around the expected cash flows and assets of a project, rather than relying solely on the balance sheets of its sponsors. For large offshore wind developments, this approach can bring together commercial lenders, institutional investors and public financial institutions to fund construction.

20-year Contracts for Difference provide revenue framework

The Vanguard projects secured 20-year Contracts for Difference (CfDs) in the UK’s Allocation Round 7. Each project was awarded an inflation-indexed strike price of £91.20 per megawatt hour (MWh), expressed in 2024 prices.

The CfD mechanism provides eligible generators with a contractual revenue framework linked to an agreed strike price and the relevant market reference price. It is designed to reduce exposure to wholesale electricity price volatility and support investment in low-carbon generation.

The awards give the projects a long-term revenue framework as they move towards construction. However, the final economics of the developments will also depend on construction costs, financing expenses, operating performance and the timing of commissioning.

The UK government published the Allocation Round 7 results in January 2026. Its published results list Norfolk Vanguard East and Norfolk Vanguard West among the successful offshore wind projects, each with a strike price of £91.20/MWh in 2024 prices.

Construction expected to begin in early 2027

Vanguard West and Vanguard East will be located between 50 and 80 kilometres off the Norfolk coast in East Anglia.

Preparatory work on the onshore infrastructure is already well advanced, including cable works and the construction of substations. Offshore construction is scheduled to begin in early 2027.

The first foundation installation for Vanguard West is planned for the first half of 2027, followed by work on Vanguard East. Both projects are expected to be fully commissioned in 2030.

The developments will use coordinated grid infrastructure intended to reduce environmental and community impacts. Their associated transmission systems will form part of the investment programme, rather than being treated as separate from the overall project cost.

Once operational, the two wind farms are expected to have the capacity to generate enough electricity to supply the equivalent of approximately three million UK homes. This is a capacity-based estimate and does not mean that the projects will supply electricity to a fixed number of households at all times.

Offshore wind investment and UK energy infrastructure

The projects add a substantial amount of planned generation capacity to the UK’s offshore wind pipeline. Their development also illustrates the financing requirements associated with large-scale renewable energy infrastructure, where construction expenditure, grid connections and long development timelines require a combination of capital sources.

The participation of 35 banks, alongside the National Wealth Fund and export credit agencies, demonstrates the range of financial institutions involved in supporting the projects. The structure also highlights the role of public-sector financial support in mobilising private investment for major infrastructure developments.

For the offshore wind supply chain, the move towards construction creates potential demand for foundations, subsea cables, electrical systems, offshore installation vessels, engineering services and specialist construction contractors. The scale of the projects means that delivery will require coordination across multiple suppliers and infrastructure workstreams.

The schedule will be an important factor. Offshore construction is expected to start in early 2027, with full commissioning targeted for 2030. The ability to maintain this timetable will depend on the progress of manufacturing, installation, grid infrastructure and other construction activities.

RWE and KKR have therefore moved the Vanguard developments beyond the financing and ownership milestones and towards the construction phase. The next major indicators will include the start of offshore works, foundation installation and progress on the associated transmission infrastructure.